Timeline 

Here’s a timeline of our house building process thus far. Feel free to review our blog posts and ask questions!

Warmly, The Richardsons

  • Reserved Lot – January 2017
  • Signed initial contract & placed SOLD sign – February 19, 2017
  • Official Design Center Appointment – March 23, 2017
  • Signed Design Center Contract – April 20, 2017
  • Visited & Decided on AudioBuys Selection – May 4, 2017
  • Building Permit Granted – May 2017
  • Preconstruction Meeting – June 27, 2017
  • Revision of Design Center Options – July 2017
  • Received Pre-appraisal – August 25, 2017
  • Broke Ground- September 1, 2017
    • Footers poured- September 11, 2017
    • Foundation poured- September 19, 2017
    • Waterproofing foundation- September 21, 2017
    • Underground plumbing- September 22, 2017
    • Poured basement/garage floor- October 19, 2017
  • Framing day 1 – October 21st
  • HVAC install – November 8th
  • Plumbing install – November 13th
  • Electrical – Started November 21st
  • Pre drywall meeting – November 28th
  • Electrical inspection passed – Dec 8th
  • Insulation in progress – Dec 12th
  • Drywall started – Dec 14th
  • Brick installation started – Dec 14th
  • Closing Date – TBD